0
0 votes
0
0 answers
80
80 views
GATE Mechanical 2026 | Question: 36
An objective function $Z$ of primal variables ( $x_{1}$ and $x_{2}$ ) is described below:\[\begin{array}{ll}\text { Minimize } Z= & 0.07 x_{1}+0.05 x_{2} \\\text { subjec...
gatecse
80
views
asked
Feb 23
Operations Research
gateme-2026
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
55
55 views
GATE Mechanical 2026 | Question: 55
The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic ( $t_{o}$ ), most likely ( $t_{m}$ ), and pessimistic ( $t_{p...
gatecse
55
views
asked
Feb 23
Operations Research
gateme-2026
numerical-answers
operations-research
production-planning-and-control
+
–
0
0 votes
0
0 answers
179
179 views
GATE Mechanical 2025 | Question: 55
A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity $D$ is _________ hours (answer i...
Shubham Sharma 2
179
views
asked
Mar 6, 2025
Operations Research
gateme-2025
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
824
824 views
GATE Mechanical 2024 | Question: 29
At the current basic feasible solution $\text{(bfs)}$ $v_{0}\left(v_{0} \in \mathbb{R}^{5}\right)$, the simplex method yields the following form of a linear programmi...
admin
824
views
asked
Feb 16, 2024
Operations Research
gateme-2024
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
1.3k
1.3k views
GATE Mechanical 2024 | Question: 55
In a supplier-retailer supply chain, the demand of each retailer, the capacity of each supplier, and the unit cost in rupees of material supply from each supplier to each...
admin
1.3k
views
asked
Feb 16, 2024
Operations Research
gateme-2024
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
1.5k
1.5k views
GATE Mechanical 2023 | Question: 4
Which one of the options given represents the feasible region of the linear programming model:$$\begin{gathered}\text { Maximize } 45 X_1+60 X_2 \\X_1 \leq 45 \\X_2 \leq ...
admin
1.5k
views
asked
May 21, 2023
Operations Research
gateme-2023
operations-research
linear-programming
quantitative-aptitude
+
–
0
0 votes
0
0 answers
686
686 views
GATE Mechanical 2022 Set 2 | Question: 22
An electric car manufacturer underestimated the January sales of car by $20$ units, while the actual sales was $120$ units. If the manufacturer uses exponential smoothing...
Arjun
686
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
296
296 views
GATE Mechanical 2022 Set 2 | Question: 31
Parts $P1 – P7$ are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completio...
Arjun
296
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
operations-research
production-planning-and-control
numerical-answers
+
–
0
0 votes
0
0 answers
488
488 views
GATE Mechanical 2022 Set 2 | Question: 32
A manufacturing unit produces two products $P1$ and $P2$. For each piece of $P1$ and $P2$, the table below provides quantities of materials $\text{M1, M2}$ and $M3$ requi...
Arjun
488
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
operations-research
production-planning-and-control
numerical-answers
+
–
0
0 votes
0
0 answers
260
260 views
GATE Mechanical 2022 Set 2 | Question: 49
A project consists of five activities $\text{(A, B, C, D and E)}$. The duration of each activity follows beta distribution. The three time estimates (in weeks) of each ac...
Arjun
260
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
389
389 views
GATE Mechanical 2022 Set 1 | Question: 11
In a linear programming problem, if a resource is not fully utilized, the shadow price of that resource ispositivenegativezeroinfinity
Arjun
389
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set1
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
424
424 views
GATE Mechanical 2022 Set 1 | Question: 32
Activities $A$ to $K$ are required to complete a project. The time estimates and the immediate predecessors of these activities are given in the table. If the project is ...
Arjun
424
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set1
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
414
414 views
GATE Mechanical 2022 Set 1 | Question: 48
An assignment problem is solved to minimize the total processing time of four jobs ($1,2,3$ and $4$) on four different machines such that each job is processed exactly by...
Arjun
414
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set1
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
279
279 views
GATE Mechanical 2021 Set 1 | Question: 28
A set of jobs $\text{A, B, C, D, E, F, G, H}$ arrive at time $t= 0$ for processing on turning and grinding machines. Each job needs to be processed in sequence first on ...
gatecse
279
views
asked
Feb 22, 2021
Operations Research
gateme-2021-set1
production-planning-and-control
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
251
251 views
GATE Mechanical 2021 Set 1 | Question: 42
Consider a single machine workstation to which jobs arrive according to a Poisson distribution with a mean arrival rate of $12$ jobs/hour. The process time of the worksta...
gatecse
251
views
asked
Feb 22, 2021
Operations Research
gateme-2021-set1
numerical-answers
operations-research
probability-and-statistics
+
–
0
0 votes
0
0 answers
343
343 views
GATE2020-ME-2: 23
Consider the following network of activities, with each activity named $\textbf{A – L}$, illustrated in the nodes of the network.The number of hours required for each act...
go_editor
343
views
asked
Sep 18, 2020
Operations Research
gateme-2020-set2
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
317
317 views
GATE2020-ME-1: 13
In the Critical Path Method $(CPM)$, the cost-time slope of an activity is given by$\dfrac{\text{Crash Cost – Normal Cost}}{\text{Crash Time}} \\$$\dfrac{\text{Normal Cos...
go_editor
317
views
asked
Feb 19, 2020
Operations Research
gateme-2020-set1
cpm
operations-research
materials-manufacturing-and-industrial-engineering
+
–
0
0 votes
0
0 answers
449
449 views
GATE ME 2012 | Question: 55
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.$\begi...
Andrijana3306
449
views
asked
Mar 19, 2018
Operations Research
gateme-2012
operations-research
cpm
+
–
1
1 vote
0
0 answers
555
555 views
GATE ME 2012 | Question: 54
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.$\begi...
Andrijana3306
555
views
asked
Mar 19, 2018
Operations Research
gateme-2012
operations-research
cpm
+
–
1
1 vote
0
0 answers
458
458 views
GATE2018-2-51
The arc lengths of a directed graph of a project are as shown in the figure. The shortest path length from node $1$ to node $6$ is __________
Arjun
458
views
asked
Feb 17, 2018
Operations Research
gateme-2018-set2
numerical-answers
+
–
0
0 votes
0
0 answers
241
241 views
GATE2016-3-25
In PERT chart, the activity time distribution isNormalBinomialPoissonBeta
Arjun
241
views
asked
Feb 24, 2017
Operations Research
gateme-2016-set3
pert
operations-research
materials-manufacturing-and-industrial-engineering
+
–
0
0 votes
0
0 answers
252
252 views
GATE2016-2-20
In a single-channel queuing model, the customer arrival rate is $12$ per hour and the serving rate is $24$ per hour. The expected time that a customer is in queue is ____...
Arjun
252
views
asked
Feb 24, 2017
Operations Research
gateme-2016-set2
numerical-answers
simple-queuing-models
operations-research
materials-manufacturing-and-industrial-engineering
+
–
0
0 votes
0
0 answers
305
305 views
GATE2015-3-8
In the notation $(a/b/c) : (d/e/f)$ for summarizing the characteristics of queuing situation, the letters $‘b’$ and $‘d’$ stand respectively forservice time distribution ...
Arjun
305
views
asked
Feb 24, 2017
Operations Research
gateme-2015-set3
simple-queuing-models
operations-research
materials-manufacturing-and-industrial-engineering
+
–
0
0 votes
0
0 answers
457
457 views
GATE Mechanical 2014 Set 3 | Question: 21
A minimal spanning tree in network flow models involvesall the nodes with cycle/loop allowedall the nodes with cycle/loop not allowedshortest path between start and end n...
Arjun
457
views
asked
Feb 19, 2017
Operations Research
gateme-2014-set3
network-flow-models
operations-research
materials-manufacturing-and-industrial-engineering
+
–
To see more, click for the
full list of questions
or
popular tags
.