Parts $P1 – P7$ are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required tor carrying out both the operations for all $7$ parts is _____________ hours.

$$\begin{array}{|c|c|} \hline
\text{Part} & \text{Milling (hours)} & \text{Polishing (hours)} \\ \hline\text{P 1} & 8  & 6 \\ \hline \text{P 2} & 3  & 2 \\ \hline\text{P 3} & 3  & 4 \\ \hline \text{P 4} & 4  & 6 \\ \hline \text{P 5} & 5  & 7 \\ \hline \text{P 6} & 6 & 4 \\ \hline \text{P 7} & 2  & 1 \\ \hline \end{array}$$

  1. $31$
  2. $33$
  3. $30$
  4. $32$
edited by

Please log in or register to answer this question.

Answer:

Related questions

0 answers
0 votes
Arjun asked Feb 15, 2022
$F(t)$ is a periodic square wave function as shown. It takes only two values, $4$ and $0$, and stays at each of these values for $1$ second before changing. What is the c...
0 answers
0 votes
0 answers
0 votes
Arjun asked Feb 15, 2022
Given $\int_{-\infty }^{\infty } e^{-x^{2}} dx = \sqrt{\pi }.$If $a$ and $b$ are positive integers, the value of $\int_{-\infty }^{\infty } e^{-a\left ( x+b \right )^{2}}...