Login
Register
Dark Mode
Brightness
Ambient Glow – Questions list
Register
Profile
Edit Profile
Messages
My favorites
My Updates
Logout
Recent questions tagged operations-research
0
0 votes
0
0 answers
76
76 views
GATE Mechanical 2026 | Question: 36
An objective function $Z$ of primal variables ( $x_{1}$ and $x_{2}$ ) is described below:\[\begin{array}{ll}\text { Minimize } Z= & 0.07 x_{1}+0.05 x_{2} \\\text { subjec...
gatecse
76
views
asked
Feb 23
Operations Research
gateme-2026
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
62
62 views
GATE Mechanical 2026 | Question: 37
Four jobs are on order in a factory. As on day $20$ of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given i...
gatecse
62
views
asked
Feb 23
Production, Planning and Control
gateme-2026
production-planning-and-control
operations-research
analytical-aptitude
+
–
0
0 votes
0
0 answers
74
74 views
GATE Mechanical 2026 | Question: 50
The actual demand for castings in a factory is $500$ units and $635$ units for the months of January $2026$ and February $2026$, respectively. The forecasted demand for J...
gatecse
74
views
asked
Feb 23
Inventory Control
gateme-2026
numerical-answers
production-planning-and-control
operations-research
quantitative-aptitude
+
–
0
0 votes
0
0 answers
83
83 views
GATE Mechanical 2026 | Question: 51
The inventory holding cost of an item is ₹ $0.50$ per unit per month and the ordering cost per order is ₹ $550$. A stockist needs to supply $10000$ units of the item per ...
gatecse
83
views
asked
Feb 23
Inventory Control
gateme-2026
numerical-answers
inventory-control
operations-research
quantitative-aptitude
+
–
0
0 votes
0
0 answers
52
52 views
GATE Mechanical 2026 | Question: 55
The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic ( $t_{o}$ ), most likely ( $t_{m}$ ), and pessimistic ( $t_{p...
gatecse
52
views
asked
Feb 23
Operations Research
gateme-2026
numerical-answers
operations-research
production-planning-and-control
+
–
1
1 vote
0
0 answers
414
414 views
GATE Mechanical 2025 | Question: 27
Considering the actual demand and the forecast for a product given in the table below, the mean forecast error and the mean absolute deviation, respectively, arePer...
Shubham Sharma 2
414
views
asked
Mar 6, 2025
Probability and Statistics
gateme-2025
operations-research
production-planning-and-control
probability-and-statistics
numerical-answers
+
–
0
0 votes
0
0 answers
414
414 views
GATE Mechanical 2025 | Question: 54
A company uses $3000$ units of a part annually. The units are priced as given in the table below. It costs ₹ $150$ to place an order. Carrying costs are $40$ percent of t...
Shubham Sharma 2
414
views
asked
Mar 6, 2025
Inventory Control
gateme-2025
numerical-answers
operations-research
production-planning-and-control
inventory-control
+
–
0
0 votes
0
0 answers
176
176 views
GATE Mechanical 2025 | Question: 55
A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity $D$ is _________ hours (answer i...
Shubham Sharma 2
176
views
asked
Mar 6, 2025
Operations Research
gateme-2025
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
894
894 views
GATE Mechanical 2024 | Question: 24
A set of jobs $\text{U, V, W, X, Y, Z}$ arrive at time $t=0$ to a production line consisting of two workstations in series. Each job must be processed by both workst...
admin
894
views
asked
Feb 16, 2024
Production, Planning and Control
gateme-2024
production-planning-and-control
operations-research
applied-mechanics-and-design
+
–
0
0 votes
0
0 answers
538
538 views
GATE Mechanical 2024 | Question: 25
A queueing system has one single server workstation that admits an infinitely long queue. The rate of arrival of jobs to the queueing system follows the Poisson dist...
admin
538
views
asked
Feb 16, 2024
Probability and Statistics
gateme-2024
operations-research
probability-and-statistics
numerical-answers
+
–
0
0 votes
0
0 answers
657
657 views
GATE Mechanical 2024 | Question: 28
A company orders gears in conditions identical to those considered in the economic order quantity $\text{(EOQ)}$ model in inventory control. The annual demand is $800...
admin
657
views
asked
Feb 16, 2024
Inventory Control
gateme-2024
numerical-answers
inventory-control
operations-research
+
–
0
0 votes
0
0 answers
807
807 views
GATE Mechanical 2024 | Question: 29
At the current basic feasible solution $\text{(bfs)}$ $v_{0}\left(v_{0} \in \mathbb{R}^{5}\right)$, the simplex method yields the following form of a linear programmi...
admin
807
views
asked
Feb 16, 2024
Operations Research
gateme-2024
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
1.3k
1.3k views
GATE Mechanical 2024 | Question: 55
In a supplier-retailer supply chain, the demand of each retailer, the capacity of each supplier, and the unit cost in rupees of material supply from each supplier to each...
admin
1.3k
views
asked
Feb 16, 2024
Operations Research
gateme-2024
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
1.5k
1.5k views
GATE Mechanical 2023 | Question: 4
Which one of the options given represents the feasible region of the linear programming model:$$\begin{gathered}\text { Maximize } 45 X_1+60 X_2 \\X_1 \leq 45 \\X_2 \leq ...
admin
1.5k
views
asked
May 21, 2023
Operations Research
gateme-2023
operations-research
linear-programming
quantitative-aptitude
+
–
0
0 votes
0
0 answers
680
680 views
GATE Mechanical 2022 Set 2 | Question: 22
An electric car manufacturer underestimated the January sales of car by $20$ units, while the actual sales was $120$ units. If the manufacturer uses exponential smoothing...
Arjun
680
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
292
292 views
GATE Mechanical 2022 Set 2 | Question: 31
Parts $P1 – P7$ are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completio...
Arjun
292
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
operations-research
production-planning-and-control
numerical-answers
+
–
0
0 votes
0
0 answers
483
483 views
GATE Mechanical 2022 Set 2 | Question: 32
A manufacturing unit produces two products $P1$ and $P2$. For each piece of $P1$ and $P2$, the table below provides quantities of materials $\text{M1, M2}$ and $M3$ requi...
Arjun
483
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
operations-research
production-planning-and-control
numerical-answers
+
–
0
0 votes
0
0 answers
256
256 views
GATE Mechanical 2022 Set 2 | Question: 49
A project consists of five activities $\text{(A, B, C, D and E)}$. The duration of each activity follows beta distribution. The three time estimates (in weeks) of each ac...
Arjun
256
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
387
387 views
GATE Mechanical 2022 Set 1 | Question: 11
In a linear programming problem, if a resource is not fully utilized, the shadow price of that resource ispositivenegativezeroinfinity
Arjun
387
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set1
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
418
418 views
GATE Mechanical 2022 Set 1 | Question: 32
Activities $A$ to $K$ are required to complete a project. The time estimates and the immediate predecessors of these activities are given in the table. If the project is ...
Arjun
418
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set1
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
406
406 views
GATE Mechanical 2022 Set 1 | Question: 48
An assignment problem is solved to minimize the total processing time of four jobs ($1,2,3$ and $4$) on four different machines such that each job is processed exactly by...
Arjun
406
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set1
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
308
308 views
GATE Mechanical 2021 Set 2 | Question: 29
A factory produces $m (i= 1,2,\cdots, m)$ products, each of which requires processing on $n(j = 1,2,\cdots, n)$ workstations. Let $a_{ij}$ be the amount of processing ti...
go_editor
308
views
asked
Mar 1, 2021
Production, Planning and Control
gateme-2021-set2
operations-research
production-planning-and-control
inventory-control
+
–
0
0 votes
0
0 answers
259
259 views
GATE Mechanical 2021 Set 2 | Question: 43
The demand and forecast of an item for five months are given in the table.$$\begin{array}{|cl|cI|cI|}\hline&\textbf{Month} & \textbf{Demand} & \textbf{Forecast} \\ \hline...
go_editor
259
views
asked
Mar 1, 2021
Production, Planning and Control
gateme-2021-set2
numerical-answers
production-planning-and-control
quantitative-aptitude
operations-research
+
–
0
0 votes
0
0 answers
273
273 views
GATE Mechanical 2021 Set 1 | Question: 28
A set of jobs $\text{A, B, C, D, E, F, G, H}$ arrive at time $t= 0$ for processing on turning and grinding machines. Each job needs to be processed in sequence first on ...
gatecse
273
views
asked
Feb 22, 2021
Operations Research
gateme-2021-set1
production-planning-and-control
operations-research
numerical-answers
+
–
1
1 vote
1
1 answer
605
605 views
GATE Mechanical 2021 Set 1 | Question: 35
Activities $\text{A, B, C}$ and $\text{D}$ form the critical path for a project with a $\text{PERT}$ network. The means and variances of the activity duration for each ac...
gatecse
605
views
asked
Feb 22, 2021
Probability and Statistics
gateme-2021-set1
numerical-answers
probability-and-statistics
operations-research
+
–
0
0 votes
0
0 answers
248
248 views
GATE Mechanical 2021 Set 1 | Question: 42
Consider a single machine workstation to which jobs arrive according to a Poisson distribution with a mean arrival rate of $12$ jobs/hour. The process time of the worksta...
gatecse
248
views
asked
Feb 22, 2021
Operations Research
gateme-2021-set1
numerical-answers
operations-research
probability-and-statistics
+
–
0
0 votes
0
0 answers
338
338 views
GATE2020-ME-2: 23
Consider the following network of activities, with each activity named $\textbf{A – L}$, illustrated in the nodes of the network.The number of hours required for each act...
go_editor
338
views
asked
Sep 18, 2020
Operations Research
gateme-2020-set2
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
403
403 views
GATE2020-ME-2: 33
The forecast for the monthly demand of a product is given in the table below:$\begin{array}{|c|c|c|} \hline \textbf{Month} & \textbf{Forecast} & \textbf{Actual Sales} \\ ...
go_editor
403
views
asked
Sep 18, 2020
Inventory Control
gateme-2020-set2
operations-research
forecasting-models
numerical-answers
+
–
0
0 votes
0
0 answers
313
313 views
GATE2020-ME-1: 13
In the Critical Path Method $(CPM)$, the cost-time slope of an activity is given by$\dfrac{\text{Crash Cost – Normal Cost}}{\text{Crash Time}} \\$$\dfrac{\text{Normal Cos...
go_editor
313
views
asked
Feb 19, 2020
Operations Research
gateme-2020-set1
cpm
operations-research
materials-manufacturing-and-industrial-engineering
+
–
0
0 votes
1
1 answer
932
932 views
GATE2020-ME-1: 23
A company is hiring to fill four managerial vacancies. The candidates are five men and three women. If every candidate is equally likely to be chosen then the probability...
go_editor
932
views
asked
Feb 19, 2020
Materials, Manufacturing and Industrial Engineering
gateme-2020-set1
numerical-answers
materials-manufacturing-and-industrial-engineering
operations-research
+
–
Page:
1
2
next »