The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship $”X<Y,Z”$ means that $X$ is predecessor of activities $Y$ and $Z$. The time to complete the activities along the critical path is ____ weeks.

$\begin{array}{|c|c|c|} \hline \text{Activity} & \text{Duration (Weeks)} & \text{Precedence Relationship} \\ \hline A & 5 & A<B, C, D \\ \hline B & 7 & B<E, F, G \\ \hline C & 10 & C<I \\ \hline D & 6 & D < G \\ \hline E & 3 & E < H \\ \hline F & 9 & F < I \\ \hline G & 7 & G < I \\ \hline H & 4 & H < I \\ \hline I & 2  & --- \\ \hline \end{array}$

  1. $17$
  2. $21$
  3. $23$
  4. $25$
in Others by (21.2k points) 4 29 72
edited by

Please log in or register to answer this question.

Welcome to GO Mechanical, where you can ask questions and receive answers from other members of the community.

1,182 questions
54 answers
21 comments
2,827 users