Following data refers to the jobs $(P, Q, R, S)$ which have arrived at a machine for scheduling. The shortest possible average flow time is __________ days.

$$\begin{array}{|l|l|} \hline \text{Job} & \text{Processing Time (days)} \\ \hline P & 15 \\ \hline Q & 9 \\ \hline R & 22 \\ \hline S & 12 \\ \hline \end{array}$$

Please log in or register to answer this question.

Related questions

0 0 votes
0 0 answers
317
317 views
Arjun asked Feb 26, 2017
317 views
Two models, $P$ and $Q$, of a product, earn profits of Rs.$100$ and Rs. $80$ per piece, respectively. Production times for $P$ and $Q$ are $5$ hours and $3$ hours, respec...
0 0 votes
0 0 answers
340
340 views
Arjun asked Feb 26, 2017
340 views
Two cutting tools with tool life equations given below are being compared:Tool $1$: $VT^{0.1}=150$Tool $2$: $VT^{0.3}=300$where $V$ is cutting speed in m/minute and $T$ i...
0 0 votes
0 0 answers
336
336 views
Arjun asked Feb 26, 2017
336 views
A sprue in a sand mould has a top diameter of $20 \: mm$ and height of $200$ mm. The velocity of the molten metal at the entry of the sprue is $0.5 \: m/s$. Assume accele...
0 0 votes
0 0 answers
429
429 views
Arjun asked Feb 26, 2017
429 views
A block of length $200$ mm is machined by a slab milling cutter $34$ mm in diameter. The depth of cut and table feed are set at $2$ mm and $18$ mm/minute, respectively. C...

Related questions

0 0 votes
0 0 answers
317
317 views
Arjun asked Feb 26, 2017
317 views
Two models, $P$ and $Q$, of a product, earn profits of Rs.$100$ and Rs. $80$ per piece, respectively. Production times for $P$ and $Q$ are $5$ hours and $3$ hours, respec...
0 0 votes
0 0 answers
340
340 views
Arjun asked Feb 26, 2017
340 views
Two cutting tools with tool life equations given below are being compared:Tool $1$: $VT^{0.1}=150$Tool $2$: $VT^{0.3}=300$where $V$ is cutting speed in m/minute and $T$ i...
0 0 votes
0 0 answers
336
336 views
Arjun asked Feb 26, 2017
336 views
A sprue in a sand mould has a top diameter of $20 \: mm$ and height of $200$ mm. The velocity of the molten metal at the entry of the sprue is $0.5 \: m/s$. Assume accele...
0 0 votes
0 0 answers
429
429 views
Arjun asked Feb 26, 2017
429 views
A block of length $200$ mm is machined by a slab milling cutter $34$ mm in diameter. The depth of cut and table feed are set at $2$ mm and $18$ mm/minute, respectively. C...