GATE2016-2-55
A project consists of $14$ activities, $A$ to $N$. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node $10$ is __________
Arjun
asked
in
Materials, Manufacturing and Industrial Engineering
Feb 24, 2017
by
Arjun
27.4k
points
gateme-2016-set2
numerical-answers
materials-manufacturing-and-industrial-engineering
operations-research
network-flow-models
0
answers
0
votes
GATE2016-2-54
A food processing company uses $25,000 \:kg$ ... on an annual basis is $20\%$ of the purchase price of the corn flour per $kg$. The optimal order quantity (in $kg$) is _____________
Arjun
asked
in
Materials, Manufacturing and Industrial Engineering
Feb 24, 2017
by
Arjun
27.4k
points
gateme-2016-set2
numerical-answers
materials-manufacturing-and-industrial-engineering
operations-research
network-flow-models
0
answers
0
votes
GATE2015-1-33
Following data refers to the activities of a project, where, node $1$ refers to the start and node $5$ ... (CP) in the network is $1$-$2$-$3$-$5$ $1$-$4$-$3$-$5$ $1$-$2$-$3$-$4$-$5$ $1$-$4$-$5$
Arjun
asked
in
Materials, Manufacturing and Industrial Engineering
Feb 24, 2017
by
Arjun
27.4k
points
gateme-2015-set1
materials-manufacturing-and-industrial-engineering
operations-research
network-flow-models
0
answers
0
votes
GATE Mechanical 2014 Set 4 | Question: 50
The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities $e$ and $f$ ... $0$ and $4$ $1$ and $4$ $2$ and $3$ $3$ and $1$
Arjun
asked
in
Materials, Manufacturing and Industrial Engineering
Feb 19, 2017
by
Arjun
27.4k
points
gateme-2014-set4
materials-manufacturing-and-industrial-engineering
operations-research
network-flow-models
0
answers
0
votes
GATE Mechanical 2014 Set 3 | Question: 21
A minimal spanning tree in network flow models involves all the nodes with cycle/loop allowed all the nodes with cycle/loop not allowed shortest path between start and end nodes all the nodes with directed arcs
Arjun
asked
in
Operations Research
Feb 19, 2017
by
Arjun
27.4k
points
gateme-2014-set3
network-flow-models
operations-research
materials-manufacturing-and-industrial-engineering
To see more, click for the
full list of questions
or
popular tags
.
Welcome to GO Mechanical, where you can ask questions and receive answers from other members of the community.
Recent Posts
GATE Mechanical Engineering Syllabus for GATE 2023 (Updated 2020)
ISRO Questions Papers for Mechanical
ISRO Mechanical and RAC Previous Year Papers
How to Apply to Colleges after GATE
GATE Mechanical Syllabus
Top Users
Jan 2023
RubySN
120 Points