A firm uses a turning center, a milling center and a grinding machine to produce two parts. The table below provides the machining time required for each part and the maximum machining time available on each machine. The profit per unit on parts $I$ and $II$ are $Rs. 40$ and $Rs. 100$, respectively. The maximum profit per week of the firm is $Rs$._________

Type of machine Machining time required for the machine part (minutes) Maximum machining time available per week (minutes)
I II
Turning machine $12$ $6$ $6000$
Milling center $4$ $10$ $4000$
Grinding Machine $2$ $3$ $1800$
in Materials, Manufacturing and Industrial Engineering 24.6k points
recategorized by

Please log in or register to answer this question.

Answer:

Related questions

0 votes
0 answers
The demand for a two-wheeler was $900$ units and $1030$ units in April $2015$ and May $2015$, respectively. The forecast for the month of April $2015$ was $850$ units. Considering a smoothing constant of $0.6$, the forecast for the month of June $2015$ is $850$ units $927$ units $965$ units $970$ units
asked Feb 24, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
0 votes
0 answers
0 votes
0 answers
0 votes
0 answers
Spot welding of two steel sheets each $2 \: mm$ thick is carried out successfully by passing $4 \: kA$ of current for $0.2$ seconds through the electrodes. The resulting weld nugget formed between the sheets is $5 \: mm$ in diameter. Assuming cylindrical shape for the nugget, the thickness of ...
asked Feb 24, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
...