A project consists of five activities $\text{(A, B, C, D and E)}$. The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor$(s)$ are listed in the table. The expected time of the project completion is ________________ weeks (in integer).

      Activity                     Time estimates (in weeks)   Immediate
  Predecessor(s)
  Optimistic 
      time
  Most likely
       time
  Pessimistic
      time 
       A           4           5            6       None
       B           1           3            5         A
       C           1           2            3         A
       D           2           4            6         C
       E           3           4            5        B, D

 