Recent questions tagged production-planning-and-control

0 0 votes
0 0 answers
58
58 views
Four jobs are on order in a factory. As on day $20$ of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given i...
0 0 votes
0 0 answers
69
69 views
The actual demand for castings in a factory is $500$ units and $635$ units for the months of January $2026$ and February $2026$, respectively. The forecasted demand for J...
0 0 votes
0 0 answers
52
52 views
The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic ( $t_{o}$ ), most likely ( $t_{m}$ ), and pessimistic ( $t_{p...
1 1 vote
0 0 answers
412
412 views
​​​​​​Considering the actual demand and the forecast for a product given in the table below, the mean forecast error and the mean absolute deviation, respectively, arePer...
0 0 votes
0 0 answers
201
201 views
Cylindrical workpieces of diameter $60 \: mm$ and length $400 \:mm$ are machined on a lathe at a cutting speed of $25 \mathrm{~m} \mathrm{~min}^{-1}$ and a feed of $0.2 ...
0 0 votes
0 0 answers
411
411 views
A company uses $3000$ units of a part annually. The units are priced as given in the table below. It costs ₹ $150$ to place an order. Carrying costs are $40$ percent of t...
0 0 votes
0 0 answers
893
893 views
​​​​​A set of jobs $\text{U, V, W, X, Y, Z}$ arrive at time $t=0$ to a production line consisting of two workstations in series. Each job must be processed by both workst...
0 0 votes
0 0 answers
1.3k
1.3k views
With reference to the Economic Order Quantity $\text{(EOQ)}$ model, which one of the options given is correct?$\text{Curve P1:}$ Total cost, $\text{Curve P2:}$ Holding co...
0 0 votes
0 0 answers
607
607 views
The demand of a certain part is $1000$ parts/year and its cost is ₹$1000$/part. The orders are placed based on the economic order quantity $\text{(EOQ)}$. The cost of ord...
0 0 votes
0 0 answers
290
290 views
Parts $P1 – P7$ are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completio...
0 0 votes
0 0 answers
480
480 views
A manufacturing unit produces two products $P1$ and $P2$. For each piece of $P1$ and $P2$, the table below provides quantities of materials $\text{M1, M2}$ and $M3$ requi...
0 0 votes
0 0 answers
334
334 views
Which one of the following is NOT a form of inventory?Raw materialsWork-in-process materialsFinished goods$\text{CNC}$ Milling Machines
0 0 votes
0 0 answers
330
330 views
The product structure diagram shows the number of different components required at each level to produce one unit of the final product $P$. If there are $50$ units of on-...
0 0 votes
0 0 answers
307
307 views
A factory produces $m (i= 1,2,\cdots, m)$ products, each of which requires processing on $n(j = 1,2,\cdots, n)$ workstations. Let $a_{ij}$ be the amount of processing ti...
0 0 votes
0 0 answers
418
418 views
Daily production capacity of a bearing manufacturing company is $30000$ bearings. The daily demand of the bearing is $15000$. The holding cost per year of keeping a beari...
0 0 votes
0 0 answers
259
259 views
The demand and forecast of an item for five months are given in the table.$$\begin{array}{|cl|cI|cI|}\hline&\textbf{Month} & \textbf{Demand} & \textbf{Forecast} \\ \hline...
0 0 votes
0 0 answers
723
723 views
The correct sequence of machining operations to be performed to finish a large diameter through hole isdrilling, boring, reamingboring, drilling, reamingdrilling, reaming...
0 0 votes
0 0 answers
272
272 views
A set of jobs $\text{A, B, C, D, E, F, G, H}$ arrive at time $t= 0$ for processing on turning and grinding machines. Each job needs to be processed in sequence first on ...
0 0 votes
0 0 answers
388
388 views
In Materials Requirement Planning, if the inventory holding cost is very high and the set up cost is zero, which one of the following lot sizing approaches should be used...
0 0 votes
0 0 answers
352
352 views
Five jobs $(J1, J2, J3, J4$ and $J5)$ need to be processes in a factory. Each job can be assigned to any of the five different machines $(M1, M2, M3, M4$ and $M5)$. The t...
0 0 votes
0 0 answers
864
864 views
A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:$\begin{array}{|c|c|c|} \h...
0 0 votes
0 0 answers
266
266 views
Which one of the following is NOT a decision taken during the aggregate production planning stage?Scheduling of machinesAmount of labour to be committedRate at which prod...
0 0 votes
0 0 answers
379
379 views
The time series forecasting method that gives equal weightage to each of the $m$ most recent observations isMoving average methodExponential smoothing with linear trendTr...
0 0 votes
0 0 answers
220
220 views
The annual requirement of rivets at a ship manufacturing company is $2000 \: kg$. The rivets are supplied in units of $1 \: kg$ costing $Rs. 25$ each. If it costs $Rs. 10...
0 0 votes
0 0 answers
192
192 views
Sales data of a product is given in the following table:$\begin{array}{|l|l|l|l|l|l|} \hline \textbf{Month} & \text{January} & \text{February} & \text{March} & \text{Apri...
0 0 votes
0 0 answers
328
328 views
A machine produces $0$, $1$ or $2$ defective pieces in a day with associated probability of $1/6$, $2/3$ and $1/6$, respectively. The mean value and the variance of the n...
To see more, click for the full list of questions or popular tags.