• recategorized by
275 views
0 0 votes

A set of jobs $\text{A, B, C, D, E, F, G, H}$ arrive at time $t= 0$  for processing on turning and grinding machines. Each job needs to be processed in sequence first on the turning machine and second on the grinding machine, and the grinding must occur immediately after turning. The processing times of the jobs are given below.

$\begin{array}{|cl|cI|cI|cI|cI|cI|cI|cI|cI|}\hline
&\text{Job} & \text{A} & \text{B} & \text{C} & \text{D} & \text{E} & \text{F} & \text{G}  & \text{H} \\ \hline &\text{Turning (minutes)} & \text{2} & \text{4} &\text{8}&\text{9} &\text{7} &\text{6} &\text{5} &\text{10} \\ \hline &\text{Grinding (minutes)} & \text{6} & \text{1} &\text{3} &\text{7} &\text{9}&\text{5} &\text{2} &\text{4} \\ \hline \end{array}$

 

If the makespan is to be minimized, then the optimal sequence in which these jobs must be processed on the turning and grinding machines is

  1. $\text{A-E-D-F-H-C-G-B}$
  2. $\text{A-D-E-F-H-C-G-B}$
  3. $\text{G-E-D-F-H-C-A-B}$
  4. $\text{B-G-C-H-F-D-E-A}$

Please log in or register to answer this question.

Related questions

0 0 votes
0 0 answers
249
249 views
gatecse asked Feb 22, 2021
249 views
Consider a single machine workstation to which jobs arrive according to a Poisson distribution with a mean arrival rate of $12$ jobs/hour. The process time of the worksta...
0 0 votes
0 0 answers
293
293 views
Arjun asked Feb 15, 2022
293 views
Parts $P1 – P7$ are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completio...
0 0 votes
0 0 answers
485
485 views
Arjun asked Feb 15, 2022
485 views
A manufacturing unit produces two products $P1$ and $P2$. For each piece of $P1$ and $P2$, the table below provides quantities of materials $\text{M1, M2}$ and $M3$ requi...
1 1 vote
1 1 answer
606
606 views
gatecse asked Feb 22, 2021
606 views
Activities $\text{A, B, C}$ and $\text{D}$ form the critical path for a project with a $\text{PERT}$ network. The means and variances of the activity duration for each ac...

Related questions

0 0 votes
0 0 answers
249
249 views
gatecse asked Feb 22, 2021
249 views
Consider a single machine workstation to which jobs arrive according to a Poisson distribution with a mean arrival rate of $12$ jobs/hour. The process time of the worksta...
0 0 votes
0 0 answers
293
293 views
Arjun asked Feb 15, 2022
293 views
Parts $P1 – P7$ are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completio...
0 0 votes
0 0 answers
485
485 views
Arjun asked Feb 15, 2022
485 views
A manufacturing unit produces two products $P1$ and $P2$. For each piece of $P1$ and $P2$, the table below provides quantities of materials $\text{M1, M2}$ and $M3$ requi...
1 1 vote
1 1 answer
606
606 views
gatecse asked Feb 22, 2021
606 views
Activities $\text{A, B, C}$ and $\text{D}$ form the critical path for a project with a $\text{PERT}$ network. The means and variances of the activity duration for each ac...
Position:
Show:
Answer:

Add Synced Question

×