0 0 votes Four jobs are on order in a factory. As on day $20$ of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.\[\begin{array}{|c|c|c|}\hline\text{Job} & \text{Due date} & \begin{array}{c}\text{Work remaining} \\\text{(in days)}\end{array} \\\hlineM & 26 & 5 \\\hlineN & 24 & 10 \\\hlineO & 28 & 10 \\\hlineP & 31 & 5 \\\hline\end{array}\]Which job(s) has/have critical ratio less than unity?Job $\text{N}$ and Job $\text{O}$Job $\text{M}$ and Job $\text{N}$Job $\text{P}$Job $\text{O}$ and Job $\text{P}$ Production, Planning and Control gateme-2026 production-planning-and-control operations-research analytical-aptitude + – ♦gatecse 58 views answer comment Share Follow Add Sync Questions 0 reply Please log in or register to add a comment.