The annual requirement of rivets at a ship manufacturing company is $2000 \: kg$. The rivets are supplied in units of $1 \: kg$ costing $Rs. 25$ each. If it costs $Rs. 100$ to place an order and the annual cost of carrying one unit is $9\%$ of its purchase cost, the cycle length of the order (in days) will be ________
in Materials, Manufacturing and Industrial Engineering 24.6k points
recategorized by

Please log in or register to answer this question.

Answer:

Related questions

0 votes
0 answers
0 votes
0 answers
0 votes
0 answers
Five jobs $(J1, J2, J3, J4$ and $J5)$ need to be processes in a factory. Each job can be assigned to any of the five different machines $(M1, M2, M3, M4$ and $M5)$. The time durations taken (in minutes) by the machines for each of the jobs, are given in the table. However, each job is assigned ...
asked Feb 9, 2019 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
0 votes
0 answers
A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below: ... estimated amount of time, the maximum duration (in weeks) of the activity $S$ without delaying the completion of the project is ________