Activities $A$ to $K$ are required to complete a project. The time estimates and the immediate predecessors of these activities are given in the table. If the project is to be completed in the minimum possible time, the latest finish time for the activity $G$ is  _______________ hours.

$$\begin{array}{|c|c|} \hline
\text{Activity} & \text{Time (hours)} & \text{Immediate predecessors} \\ \hline \text{A} & 2 & – \\ \hline
\text{B} & 3 & – \\ \hline \text{C} & 2 & – \\ \hline \text{D} & 4 & \text{A} \\ \hline \text{E} & 5 & \text{B} \\ \hline \text{F} & 4 & \text{B} \\ \hline \text{G} & 3 & \text{C} \\ \hline \text{H} & 10 & \text{D, E} \\ \hline \text{I} & 5 & \text{F} \\ \hline \text{J} & 8 & \text{G} \\ \hline \text{K} & 3 & \text{H, I, J} \\ \hline
\end{array}$$

  1. $5$
  2. $10$
  3. $8$
  4. $9$
edited by

Please log in or register to answer this question.

Answer:

Related questions

0 answers
0 votes
0 answers
0 votes
Arjun asked Feb 15, 2022
The Fourier series expansion of $x^{3}$ in the interval $-1 \leq x < 1$ with periodic continuation hasonly sine termsonly cosine termsboth sine and cosine termsonly sine ...
0 answers
0 votes
Arjun asked Feb 15, 2022
If $A = \begin{bmatrix} 10 & 2k +5 \\ 3k - 3 & k +5 \end{bmatrix}$ is a symmetric matrix, the value of $k$ is __________________.$8$$5$$-0.4$$\frac{1 + \sqrt{1561}}{12}$...