recategorized by
548 views
1 1 vote

For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.

$\begin{array} {}\textbf{Activity} & \textbf{Predecessors} & \textbf{Duration (days)} \\ a & – & 3 \\ b & a & 4 \\ c & a & 5 \\ d & a & 4 \\ e & b & 2 \\ f & d &  9 \\ g & c,e & 6 \\ h & f,g & 2 \end{array}$

The critical path for the project is

  1. $a-b-e-g-h$
  2. $a-c-g-h$
  3. $a-d-f-h$
  4. $a-b-c-f-h$

Please log in or register to answer this question.

Related questions

0 0 votes
0 0 answers
443
443 views
Andrijana3306 asked Mar 19, 2018
443 views
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.$\begi...
0 0 votes
0 0 answers
312
312 views
go_editor asked Feb 19, 2020
312 views
In the Critical Path Method $(CPM)$, the cost-time slope of an activity is given by$\dfrac{\text{Crash Cost – Normal Cost}}{\text{Crash Time}} \\$$\dfrac{\text{Normal Cos...
1 1 vote
0 0 answers
643
643 views
Andrijana3306 asked Mar 19, 2018
643 views
Which of the following assertions are $\textbf{CORRECT}$?Adding $7$ to each entry in a list adds $7$ to the mean of the list.Adding $7$ to each entry in a list adds $7$ t...
1 1 vote
0 0 answers
359
359 views
Andrijana3306 asked Mar 19, 2018
359 views
Wanted Temporary, Part-time persons for the post of Field Interviewer to conduct personal interviews to collect and collate economic data. Requirements: High-school pass,...

Related questions

0 0 votes
0 0 answers
443
443 views
Andrijana3306 asked Mar 19, 2018
443 views
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.$\begi...
0 0 votes
0 0 answers
312
312 views
go_editor asked Feb 19, 2020
312 views
In the Critical Path Method $(CPM)$, the cost-time slope of an activity is given by$\dfrac{\text{Crash Cost – Normal Cost}}{\text{Crash Time}} \\$$\dfrac{\text{Normal Cos...
1 1 vote
0 0 answers
643
643 views
Andrijana3306 asked Mar 19, 2018
643 views
Which of the following assertions are $\textbf{CORRECT}$?Adding $7$ to each entry in a list adds $7$ to the mean of the list.Adding $7$ to each entry in a list adds $7$ t...
1 1 vote
0 0 answers
359
359 views
Andrijana3306 asked Mar 19, 2018
359 views
Wanted Temporary, Part-time persons for the post of Field Interviewer to conduct personal interviews to collect and collate economic data. Requirements: High-school pass,...
Position:
Show:
Answer:

Add Synced Question

×