Consider the following network of activities, with each activity named $\textbf{A – L}$, illustrated in the nodes of the network.

The number of hours required for each activity is shown alongside the nodes. The slack on the activity $\textbf{L}$, is _______ hours.

retagged by

Please log in or register to answer this question.

Answer: