0 0 votes A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity $D$ is _________ hours (answer in integer). Activity Immediate predecessor Duration (hours) $A$ - $4$ $B$ $A$ $8$ $C$ $A$ $5$ $D$ $B$ $2$ $E$ $B$ $7$ $F$ $C$ $6$ $G$ $D$ $3$ $H$ $E, F, G$ $9$ Operations Research gateme-2025 numerical-answers operations-research + – ♦Shubham Sharma 2 187 views answer comment Share Follow Add Sync Questions 0 reply Please log in or register to add a comment.