A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity $D$ is _________ hours (answer in integer).

Activity Immediate predecessor Duration (hours)
$A$ - $4$
$B$ $A$ $8$
$C$ $A$ $5$
$D$ $B$ $2$
$E$ $B$ $7$
$F$ $C$ $6$
$G$ $D$ $3$
$H$ $E, F, G$ $9$

 

Please log in or register to answer this question.

Related questions

1 1 vote
0 0 answers
426
426 views
Shubham Sharma 2 asked Mar 6, 2025
426 views
​​​​​​Considering the actual demand and the forecast for a product given in the table below, the mean forecast error and the mean absolute deviation, respectively, arePer...
0 0 votes
0 0 answers
433
433 views
Shubham Sharma 2 asked Mar 6, 2025
433 views
A company uses $3000$ units of a part annually. The units are priced as given in the table below. It costs ₹ $150$ to place an order. Carrying costs are $40$ percent of t...
0 0 votes
0 0 answers
68
68 views
gatecse asked Feb 23
68 views
The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic ( $t_{o}$ ), most likely ( $t_{m}$ ), and pessimistic ( $t_{p...
0 0 votes
0 0 answers
1.3k
1.3k views
admin asked Feb 16, 2024
1,313 views
In a supplier-retailer supply chain, the demand of each retailer, the capacity of each supplier, and the unit cost in rupees of material supply from each supplier to each...

Related questions

1 1 vote
0 0 answers
426
426 views
Shubham Sharma 2 asked Mar 6, 2025
426 views
​​​​​​Considering the actual demand and the forecast for a product given in the table below, the mean forecast error and the mean absolute deviation, respectively, arePer...
0 0 votes
0 0 answers
433
433 views
Shubham Sharma 2 asked Mar 6, 2025
433 views
A company uses $3000$ units of a part annually. The units are priced as given in the table below. It costs ₹ $150$ to place an order. Carrying costs are $40$ percent of t...
0 0 votes
0 0 answers
68
68 views
gatecse asked Feb 23
68 views
The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic ( $t_{o}$ ), most likely ( $t_{m}$ ), and pessimistic ( $t_{p...
0 0 votes
0 0 answers
1.3k
1.3k views
admin asked Feb 16, 2024
1,313 views
In a supplier-retailer supply chain, the demand of each retailer, the capacity of each supplier, and the unit cost in rupees of material supply from each supplier to each...
Position:
Show:
Answer:

Add Synced Question

×