GATE Mechanical 2026 | Question: 36
An objective function $Z$ of primal variables ( $x_{1}$ and $x_{2}$ ) is described below:\[\begin{array}{ll}\text { Minimize } Z= & 0.07 x_{1}+0.05 x_{2} \\\text { subjec...
gatecse
107
views
asked
Feb 23
Operations Research
gateme-2026
operations-research
+
–
0
0 votes
0
0 answers
77
77 views
GATE Mechanical 2026 | Question: 55
The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic ( $t_{o}$ ), most likely ( $t_{m}$ ), and pessimistic ( $t_{p...
gatecse
77
views
asked
Feb 23
Operations Research
gateme-2026
numerical-answers
operations-research
production-planning-and-control
+
–
0
0 votes
0
0 answers
197
197 views
GATE Mechanical 2025 | Question: 55
A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity $D$ is _________ hours (answer i...
Shubham Sharma 2
197
views
asked
Mar 6, 2025
Operations Research
gateme-2025
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
864
864 views
GATE Mechanical 2024 | Question: 29
At the current basic feasible solution $\text{(bfs)}$ $v_{0}\left(v_{0} \in \mathbb{R}^{5}\right)$, the simplex method yields the following form of a linear programmi...
admin
864
views
asked
Feb 16, 2024
Operations Research
gateme-2024
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
1.3k
1.3k views
GATE Mechanical 2024 | Question: 55
In a supplier-retailer supply chain, the demand of each retailer, the capacity of each supplier, and the unit cost in rupees of material supply from each supplier to each...
admin
1.3k
views
asked
Feb 16, 2024
Operations Research
gateme-2024
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
1.5k
1.5k views
GATE Mechanical 2023 | Question: 4
Which one of the options given represents the feasible region of the linear programming model:$$\begin{gathered}\text { Maximize } 45 X_1+60 X_2 \\X_1 \leq 45 \\X_2 \leq ...
admin
1.5k
views
asked
May 21, 2023
Operations Research
gateme-2023
operations-research
linear-programming
quantitative-aptitude
+
–
0
0 votes
0
0 answers
707
707 views
GATE Mechanical 2022 Set 2 | Question: 22
An electric car manufacturer underestimated the January sales of car by $20$ units, while the actual sales was $120$ units. If the manufacturer uses exponential smoothing...
Arjun
707
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
314
314 views
GATE Mechanical 2022 Set 2 | Question: 31
Parts $P1 – P7$ are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completio...
Arjun
314
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
operations-research
production-planning-and-control
numerical-answers
+
–
0
0 votes
0
0 answers
520
520 views
GATE Mechanical 2022 Set 2 | Question: 32
A manufacturing unit produces two products $P1$ and $P2$. For each piece of $P1$ and $P2$, the table below provides quantities of materials $\text{M1, M2}$ and $M3$ requi...
Arjun
520
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
operations-research
production-planning-and-control
numerical-answers
+
–
0
0 votes
0
0 answers
286
286 views
GATE Mechanical 2022 Set 2 | Question: 49
A project consists of five activities $\text{(A, B, C, D and E)}$. The duration of each activity follows beta distribution. The three time estimates (in weeks) of each ac...
Arjun
286
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set2
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
410
410 views
GATE Mechanical 2022 Set 1 | Question: 11
In a linear programming problem, if a resource is not fully utilized, the shadow price of that resource ispositivenegativezeroinfinity
Arjun
410
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set1
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
451
451 views
GATE Mechanical 2022 Set 1 | Question: 32
Activities $A$ to $K$ are required to complete a project. The time estimates and the immediate predecessors of these activities are given in the table. If the project is ...
Arjun
451
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set1
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
438
438 views
GATE Mechanical 2022 Set 1 | Question: 48
An assignment problem is solved to minimize the total processing time of four jobs ($1,2,3$ and $4$) on four different machines such that each job is processed exactly by...
Arjun
438
views
asked
Feb 15, 2022
Operations Research
gateme-2022-set1
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
302
302 views
GATE Mechanical 2021 Set 1 | Question: 28
A set of jobs $\text{A, B, C, D, E, F, G, H}$ arrive at time $t= 0$ for processing on turning and grinding machines. Each job needs to be processed in sequence first on ...
gatecse
302
views
asked
Feb 22, 2021
Operations Research
gateme-2021-set1
production-planning-and-control
operations-research
numerical-answers
+
–
0
0 votes
0
0 answers
274
274 views
GATE Mechanical 2021 Set 1 | Question: 42
Consider a single machine workstation to which jobs arrive according to a Poisson distribution with a mean arrival rate of $12$ jobs/hour. The process time of the worksta...
gatecse
274
views
asked
Feb 22, 2021
Operations Research
gateme-2021-set1
numerical-answers
operations-research
probability-and-statistics
+
–
0
0 votes
0
0 answers
362
362 views
GATE2020-ME-2: 23
Consider the following network of activities, with each activity named $\textbf{A – L}$, illustrated in the nodes of the network.The number of hours required for each act...
go_editor
362
views
asked
Sep 18, 2020
Operations Research
gateme-2020-set2
numerical-answers
operations-research
+
–
0
0 votes
0
0 answers
336
336 views
GATE2020-ME-1: 13
In the Critical Path Method $(CPM)$, the cost-time slope of an activity is given by$\dfrac{\text{Crash Cost – Normal Cost}}{\text{Crash Time}} \\$$\dfrac{\text{Normal Cos...
go_editor
336
views
asked
Feb 19, 2020
Operations Research
gateme-2020-set1
cpm
operations-research
materials-manufacturing-and-industrial-engineering
+
–
0
0 votes
0
0 answers
468
468 views
GATE ME 2012 | Question: 55
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.$\begi...
Andrijana3306
468
views
asked
Mar 19, 2018
Operations Research
gateme-2012
operations-research
cpm
+
–
1
1 vote
0
0 answers
570
570 views
GATE ME 2012 | Question: 54
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.$\begi...
Andrijana3306
570
views
asked
Mar 19, 2018
Operations Research
gateme-2012
operations-research
cpm
+
–
1
1 vote
0
0 answers
471
471 views
GATE2018-2-51
The arc lengths of a directed graph of a project are as shown in the figure. The shortest path length from node $1$ to node $6$ is __________
Arjun
471
views
asked
Feb 17, 2018
Operations Research
gateme-2018-set2