Assume that the surface roughness profile is triangular as shown schematically in the figure. If the peak to valley height is $20 \mu m$, the central line average surface roughness $R_{a}$ (in $\mu m$) is

  1. $5$
  2. $6.67$
  3. $10$
  4. $20$
in Materials, Manufacturing and Industrial Engineering 24.6k points
recategorized by

Please log in or register to answer this question.

Answer:

Related questions

0 votes
0 answers
Two cutting tools with tool life equations given below are being compared: Tool $1$: $VT^{0.1}=150$ Tool $2$: $VT^{0.3}=300$ where $V$ is cutting speed in m/minute and $T$ is tool life in minutes. The breakeven cutting speed beyond which Tool $2$ will have a higher tool life is ________ m/minute.
asked Feb 27, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
0 votes
0 answers
A sprue in a sand mould has a top diameter of $20 \: mm$ and height of $200$ mm. The velocity of the molten metal at the entry of the sprue is $0.5 \: m/s$. Assume acceleration due to gravity as $9.8 \: m/s^{2}$ and neglect all losses. If the mould is well ventilated, the velocity (upto $3$ decimal points accuracy) of the molten metal at the bottom of the sprue is _________ $m/s$
asked Feb 27, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
0 votes
0 answers
A block of length $200$ mm is machined by a slab milling cutter $34$ mm in diameter. The depth of cut and table feed are set at $2$ mm and $18$ mm/minute, respectively. Considering the approach and the over travel of the cutter to be same, the minimum estimated machining time per pass is ________ minutes.
asked Feb 27, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
0 votes
0 answers
Following data refers to the jobs $(P, Q, R, S)$ which have arrived at a machine for scheduling. The shortest possible average flow time is __________ days. $\begin{array}{|l|l|} \hline \text{Job} & \text{Processing Time (days)} \\ \hline P & 15 \\ \hline Q & 9 \\ \hline R & 22 \\ \hline S & 12 \\ \hline \end{array}$
asked Feb 27, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
0 votes
0 answers
Two models, $P$ and $Q$, of a product, earn profits of Rs.$100$ and Rs. $80$ per piece, respectively. Production times for $P$ and $Q$ are $5$ hours and $3$ hours, respectively, while the total production time available is $150$ hours. For a total batch size of $40$, to maximise profit, the number of units of $P$ to be produced is ________.
asked Feb 27, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
...