Circular arc on a part profile is being machined on a vertical CNC milling machine. CNC part program using metric units with absolute dimensions is listed below:

$\begin{array}{} \hline N60& G01 &  X & 30 & Y & 55 & Z & -5&  F50 \\ N70&  G02& X&  50 & Y & 35 & R & 20 \\ N80 & G01 & Z & 5  \\ \hline \end{array}$

The coordinates of the centre of the circular arc are:

  1. $(30, 55)$
  2. $(50, 55)$
  3. $(50, 35)$
  4. $(30, 35)$
in Materials, Manufacturing and Industrial Engineering 24.6k points
recategorized by

Please log in or register to answer this question.

Answer:

Related questions

0 votes
0 answers
Which one of the following statements is TRUE for the ultrasonic machining (USM) process? In USM, the tool vibrates at subsonic frequency. USM does not employ magnetostrictive transducer. USM is an excellent process for machining ductile materials. USM often uses a slurry comprising abrasive-particles and water.
asked Feb 27, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
0 votes
0 answers
Two cutting tools with tool life equations given below are being compared: Tool $1$: $VT^{0.1}=150$ Tool $2$: $VT^{0.3}=300$ where $V$ is cutting speed in m/minute and $T$ is tool life in minutes. The breakeven cutting speed beyond which Tool $2$ will have a higher tool life is ________ m/minute.
asked Feb 27, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
0 votes
0 answers
A sprue in a sand mould has a top diameter of $20 \: mm$ and height of $200$ mm. The velocity of the molten metal at the entry of the sprue is $0.5 \: m/s$. Assume acceleration due to gravity as $9.8 \: m/s^{2}$ and neglect all losses. If the mould is well ventilated, the velocity (upto $3$ decimal points accuracy) of the molten metal at the bottom of the sprue is _________ $m/s$
asked Feb 27, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
0 votes
0 answers
A block of length $200$ mm is machined by a slab milling cutter $34$ mm in diameter. The depth of cut and table feed are set at $2$ mm and $18$ mm/minute, respectively. Considering the approach and the over travel of the cutter to be same, the minimum estimated machining time per pass is ________ minutes.
asked Feb 27, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
0 votes
0 answers
Following data refers to the jobs $(P, Q, R, S)$ which have arrived at a machine for scheduling. The shortest possible average flow time is __________ days. $\begin{array}{|l|l|} \hline \text{Job} & \text{Processing Time (days)} \\ \hline P & 15 \\ \hline Q & 9 \\ \hline R & 22 \\ \hline S & 12 \\ \hline \end{array}$
asked Feb 27, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
...