GATE Mechanical 2014 Set 3 | Question: 50
Consider the given project network, where numbers along various activities represent the normal time. The free float on activity $4$-$6$ and the project duration, respectively, are $2$, $13$ $0$, $13$ $-2$, $13$ $2$, $12$
Consider the given project network, where numbers along various activities represent the normal time. The free float on activity $4$-$6$ and the project duration, respect...