0 0 votes The current erection cost of a structure is $Rs$. $13,200$. If the labour wages per day increase by $1/5$ of the current wages and the working hours decrease by $1/24$ of the current period, then the new cost of erection in $Rs$. is $16,500$ $15,180$ $11,000$ $10,120$ Quantitative Aptitude gateme-2013 numerical-ability work-time + – piyag476 306 views answer comment Share Follow Add Sync Questions 0 reply Please log in or register to add a comment.