0 votes 0 votes A project consists of $7$ activities. The network along with the time durations (in days) for various activities is shown in the figure. The minimum time (in days) for completion of the project is_________ Heat Transfer gateme-2015-set2 numerical-answers radiation-network-analysis heat-transfer fluid-mechanics-and-thermal-science + – Arjun asked Feb 24, 2017 • recategorized Mar 4, 2021 by Lakshman Bhaiya ♦Arjun 28.5k points answer See all 0 reply