It takes $30$ minutes to empty a half-full tank by draining it at a constant rate. It is decided to simultaneously pump water into the half-full tank while draining it. What is the rate at which water has to be pumped in so that it gets fully filled in $10$ minutes?

  1. $4$ times the draining rate
  2. $3$ times the draining rate
  3. $2.5$ times the draining rate
  4. $2$ times the draining rate

Please log in or register to answer this question.

Related questions

15 15 votes
6 answers 6 answers
2.2k
2.2k views
Arjun asked Feb 9, 2019
2,244 views
Two pipes $P$ and $Q$ can fill a tank in $6$ hours and $9$ hours respectively, while a third pipe $R$ can empty the tank in $12$ hours. Initially, $P$ and $R$ are open f...
0 0 votes
0 0 answers
291
291 views
Arjun asked Feb 24, 2017
291 views
$P$, $Q$, $R$ and $S$ are working on a project. $Q$ can finish the task in $25$ days, working alone for $12$ hours a day. $R$ can finish the task in $50$ days, working al...
8 8 votes
2 answers 2 answers
1.9k
1.9k views
go_editor asked Sep 18, 2020
1,855 views
IT was estimated that $52$ men can complete a strip in a newly constructed highway connecting cities $P$ and $Q$ in $10$ days, Due to an emergency, $12$ men were sent to ...
12 12 votes
4 answers 4 answers
3.2k
3.2k views
Arjun asked Feb 17, 2018
3,193 views
A contract is to be completed in $52$ days and $125$ identical robots were employed, each operational for $7$ hours a day. After $39$ days, five-seventh of the work was c...

Related questions

15 15 votes
6 answers 6 answers
2.2k
2.2k views
Arjun asked Feb 9, 2019
2,244 views
Two pipes $P$ and $Q$ can fill a tank in $6$ hours and $9$ hours respectively, while a third pipe $R$ can empty the tank in $12$ hours. Initially, $P$ and $R$ are open f...
0 0 votes
0 0 answers
291
291 views
Arjun asked Feb 24, 2017
291 views
$P$, $Q$, $R$ and $S$ are working on a project. $Q$ can finish the task in $25$ days, working alone for $12$ hours a day. $R$ can finish the task in $50$ days, working al...
8 8 votes
2 answers 2 answers
1.9k
1.9k views
go_editor asked Sep 18, 2020
1,855 views
IT was estimated that $52$ men can complete a strip in a newly constructed highway connecting cities $P$ and $Q$ in $10$ days, Due to an emergency, $12$ men were sent to ...
12 12 votes
4 answers 4 answers
3.2k
3.2k views
Arjun asked Feb 17, 2018
3,193 views
A contract is to be completed in $52$ days and $125$ identical robots were employed, each operational for $7$ hours a day. After $39$ days, five-seventh of the work was c...
Position:
Show:
Answer:

Add Synced Question

×