A contract is to be completed in $52$ days and $125$ identical robots were employed, each operational for $7$ hours a day. After $39$ days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for $8$ hours a day?
- $50$
- $89$
- $146$
- $175$