In a linear arc welding process, the heat input per unit length is inversely proportional to

  1. welding current
  2. welding voltage
  3. welding speed
  4. duty cycle of the power source
in Materials, Manufacturing and Industrial Engineering 24.6k points
recategorized by

Please log in or register to answer this question.

Answer:

Related questions

0 votes
0 answers
0 votes
0 answers
0 votes
0 answers
During a TIG welding process, the arc current and arc voltage were $50$ $A$ and $60$ $V$, respectively, when the welding speed was $150$ $mm/min$. In another process, the TIG welding is carried out at a welding speed of $120$ $mm/min$ at the same arc voltage and heat input ... so that weld quality remains the same. The welding current (in $A$) for this process is $40.00$ $44.72$ $55.90$ $62.25$
asked Feb 24, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
0 votes
0 answers
The solidification time of a casting is proportional to $\left( \dfrac{V}{A} \right )^2$, where $V$ is the volume of the casting and $A$ is the total casting surface area losing heat. Two cubes of same material and size are cast using sand casting process. The top face of one of the cubes ... face insulated to that of the other cube is $\dfrac{25}{36} \\$ $\dfrac{36}{25} \\$ $1 \\$ $\dfrac{6}{5}$
asked Feb 24, 2017 in Materials, Manufacturing and Industrial Engineering Arjun 24.6k points
...