For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.

$\begin{array} {}\textbf{Activity} & \textbf{Predecessors} & \textbf{Duration (days)} \\ a & – & 3 \\ b & a & 4 \\ c & a & 5 \\ d & a & 4 \\ e & b & 2 \\ f & d &  9 \\ g & c,e & 6 \\ h & f,g & 2 \end{array}$

If the duration of the activity $f$ alone is changed from $9$ to $10$, then the

  1. critical path remains the same and the total duration to complete the project changed to $19$ days
  2. critical path and the total duration to complete the project remain the same
  3. critical path changes but the total duration to complete the project remain the same
  4. critical path changes but the total duration to complete the project changes to $17$ days
recategorized by

Please log in or register to answer this question.

Answer:

Related questions

0 answers
1 votes
Andrijana3306 asked Mar 19, 2018
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.$\begi...
0 answers
0 votes
Andrijana3306 asked Mar 19, 2018
At $x=0$, the function $f(x)=x^3+1$ hasa maximum valuea minimum valuea singularitya point of inflection
0 answers
0 votes
Andrijana3306 asked Mar 19, 2018
$\underset{x \rightarrow 0}{\lim} \bigg( \dfrac{1- \cos x}{x^2} \bigg)$ is$1/4$$1/2$$1$$2$
0 answers
0 votes